Activity attributes
Input/Output
Activity attributes extend the description of the activity. They include more detailed descriptions, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity attributes can also be used to identify the place where the work has to be performed, the project calendar the activity is assigned to, and the type of effort involved.
Created in:
Updated in:
- Sequence Activities (P)
- Estimate Activity Resources (P)
- Estimate Activity Durations (P)
- Develop Schedule (P)
Input to:
- Sequence Activities (P)
- Estimate Activity Resources (P)
- Estimate Activity Durations (P)
- Develop Schedule (P)
Part of: